GoodWe ES-US + Lynx FH-US + ABD Installation Guide

GoodWe ES-US + Lynx FH-US + ABD Installation Guide

GoodWe ES-US + Lynx FH-US + ABD Installation Guide

This article summarizes the key installation steps for the GoodWe ES-US hybrid inverter, Lynx FH-US battery, and ABD backup device.

⚠️ Important:

This article is a condensed installer reference. Always follow the latest GoodWe manuals, project plan set, NEC requirements, and AHJ guidelines before energizing the system.


FULL PDF VERSION OF THIS GUIDE (CLICK HERE)

GoodWe Inverter manual (CLICK HERE) 


GoodWe ABD manual (CLICK HERE) 


GoodWe Lynx battery manual (CLICK HERE) 



System Overview

A typical GoodWe storage system includes three primary components.

ES-US Hybrid Inverter

  • 5–11.4 kW split-phase hybrid inverter

  • Up to 4 MPPT inputs

  • Battery voltage range: 80–495 V

  • Continuous charge/discharge: 50 A

  • PV maximum voltage: 600 VDC

Lynx FH-US Battery

  • Stackable high-voltage battery system

  • 3–6 battery modules per stack

  • Capacity range: 9.6–19.2 kWh

  • BMS communication via CAN

ABD Backup Device

  • Whole-home or partial backup switching

  • Split-phase 120/240 V

  • Inverter breaker options: 40 A or 63 A

  • Type 3R / IP44 outdoor enclosure


System Architecture

Two system layouts are commonly used.

Whole-Home Backup

The ABD disconnects the grid during outages and the inverter/battery powers the main service panel.

Partial Backup

The ABD feeds a backup loads panel containing critical circuits.

Inverter ModelOutputAC BreakerABD Breaker
GW5000-ES-US5.0 kW30 A40 A
GW6000-ES-US6.0 kW35 A40 A
GW7600-ES-US7.6 kW40 A40 A
GW9600-ES-US9.6 kW50 A63 A
GW11K4-ES-US11.4 kW60 A63 A

Installation Requirements

Install equipment in a dry, ventilated location away from heat sources and flammable materials.

Inverter Clearance

DirectionClearance
Top500 mm
Bottom300 mm
Sides200 mm

Maximum mounting tilt: 15° back

Lynx Battery Clearance

RequirementValue
OrientationVertical only
Top/Sides300 mm
Between stacks300–600 mm

Battery must be installed on a fire-resistant surface.

ABD Clearance

DirectionClearance
Sides200 mm
Bottom300 mm
Working space500 mm

Step 1 — Mount the ES-US Inverter

  1. Install mounting bracket on structural wall.

  2. Drill 10 mm holes (80 mm deep) for expansion anchors on concrete walls.

  3. Hang inverter on bracket.

  4. Verify inverter is vertical or ≤15° back tilt.


Step 2 — Install the Lynx Battery Stack

  1. Install base and leveling feet.

  2. Place base with arrow facing wall.

  3. Stack battery modules from bottom to top.

  4. Install PCU on top module.

  5. Secure with wall locking brackets.

Battery Capacity Options

ModulesCapacityNominal Voltage
39.6 kWh192 V
412.8 kWh256 V
516.0 kWh320 V
619.2 kWh384 V

Up to 8 battery stacks may be paralleled, provided all stacks have the same capacity.


Step 3 — Connect PV, Battery, and AC Wiring

PV Wiring

  • Max PV voltage: 600 VDC

  • Max MPPT current: 16 A

  • Max short-circuit current: 23.4 A

  • PV array must be ungrounded

  • Insulation resistance > 100 kΩ

Battery Wiring

Typical cable sizes:

ConnectionCable
Battery DC6 AWG Cu
Ground (PE)10 AWG Cu

Connections:

  • BAT+

  • BAT−

  • Ground busbar

Battery communication uses CAN via EMS port.


Step 4 — Install the ABD Backup Device

Conduit Requirements

PathConduit Size
Grid input2 in
Load output2 in
Inverter connection1 in

Typical Conductor Sizes

ConnectionCable
Grid / Load (ABD200)4/0 AWG
Grid / Load (ABD100)3 AWG
Inverter AC6–8 AWG
Inverter PE10 AWG

Install CT sensors with the correct orientation on service conductors.


Step 5 — Communication Wiring

DeviceCable
Battery CAN24–16 AWG
ABD communicationCAT5e RJ45
Meter / E-STOP / GEN24–16 AWG

When an ABD is used, a separate inverter meter connection is not required.


Step 6 — Power-On Sequence

Before energizing the system confirm:

✔ Equipment securely mounted
✔ Conductors and communications connected
✔ Covers installed
✔ Unused ports sealed

Startup Order

  1. ABD main breaker

  2. ABD inverter breaker

  3. Inverter AC switch

  4. Battery breaker and battery switch

  5. PV DC isolator

  6. Inverter DC switch


Step 7 — Commissioning

Use the SolarGo App.

  1. Connect to inverter via Bluetooth or WiFi

  2. Configure inverter parameters

  3. Select battery model LX F-H-US

  4. Verify backup operation and communications

  5. Register plant in SEMS Portal

⚠ If Battery Communication Failure appears, reopen battery settings and confirm LX F-H-US.


Key Specifications

ParameterValue
Battery voltage range80–495 V
PV max voltage600 V
Max MPPT current16 A
Max charge/discharge50 A

Installer Tip

This guide summarizes the official manuals for:

  • GoodWe ES-US inverter

  • GoodWe ABD backup device

  • GoodWe Lynx FH-US battery

Always verify system design, conductor sizing, and protection requirements against the latest manufacturer documentation before commissioning.

FULL PDF VERSION HERE


    • Related Articles

    • IronRidge Rooftop Installation Video

      How to Install the IronRidge Racking System Check out the short video below to learn how to install the IronRidge Racking System on a rooftop. This video will go over the basics of the IronRidge Racking System. For more detailed instructions download ...
    • Tesla Inverter installtion Guide

      Tesla Solar Inverter Overview The Tesla Solar Inverter is a crucial component of Tesla's solar energy solutions, converting DC power from solar panels into AC power for home use. . It's designed for seamless integration with Tesla's ecosystem, ...
    • Tesla Powerwall 3

      Tesla Powerwall 3 Overview The Tesla Powerwall 3 is a fully integrated solar and battery system designed to accelerate the transition to sustainable energy. It offers whole-home backup, cost savings, and energy independence by allowing homeowners to ...
    • Solar Conduit in the Attic

      Solar Conduit in the Attic — Best Practices & Requirements Running conduit through an attic is a common part of many solar installations. The goal is to keep the wiring protected, code‑compliant, and watertight as it transitions from the roof into ...
    • Enphase IQ Battery 10C Training (4th Gen)

      This Article is to help guide you through the Enphase online training, which is necessary to complete the installation of your solar system with Enphase IQ batteries. To complete the Enphase Encharge certification process, you will need to go through ...