Solis Solarator + Renon Xcellent Plu

Solis Solarator + Renon Xcellent Plu

Solis S6 16kW + Renon Xcellent Plus Installation Guide

This article summarizes the key installation steps for the Solis S6-EH2P16K03 split-phase hybrid inverter and the Renon Xcellent Plus-US battery.

⚠️ Important:
This article is a condensed installer reference. Always follow the latest Solis and Renon manuals, project plan set, NEC requirements, AHJ guidance, and the current approved battery compatibility documents before energizing the system.

FULL PDF VERSION OF THIS GUIDE (CLICK HERE)

Solis inverter manual (CLICK HERE)

Renon battery manual (CLICK HERE)

SolisCloud local setup video (CLICK HERE)

System Overview

A typical Solis / Renon storage system includes two primary components.

Solis S6 16kW Hybrid Inverter

16 kW split-phase hybrid inverter

3 MPPT inputs

48 V battery platform

Integrated 200 A pass-through / bypass

Smart port for generator, AC coupling, or controllable loads

Up to 290 A max battery-side charge / discharge capability

Solis’s current US product page for the S6-EH2P(9.6–16)K03-SV-YD-L-US family lists 3 MPPTs, 48 V battery architecture, smart port support, integrated 200 A pass-through / bypass, and up to 290 A battery-side current.

Renon Xcellent Plus-US Battery

Low-voltage LiFePO4 battery system

16 kWh nominal energy

51.2 V nominal voltage

190 A max charge / discharge current

CAN / RS485 communication

Floor or wall mounting depending model / hardware configuration

Renon’s current product page and April 2025 user manual list 16 kWh nominal energy, 51.2 V nominal voltage, LiFePO4 chemistry, 190 A max charging/discharging current, and CAN / RS485 communication.

System Architecture

A typical Solis / Renon system uses the inverter’s integrated backup architecture rather than a separate external backup box. The utility feeds the service equipment, the inverter connects to grid / backed-up loads / PV / battery, and the smart port can be configured for generator or controllable-load use as required by the design. Solis describes this inverter family as supporting whole-home backup, smart-port integration, and integrated 200 A pass-through / bypass.

Installation Requirements

Install equipment in a dry, ventilated location away from direct heat, corrosives, and flammable materials. Maintain the manufacturer-required clearances and use only code-compliant mounting surfaces and conductor / OCP sizing from the approved plan set. The GoodWe reference guide you shared uses a condensed “installation requirements” section with inverter siting, battery siting, and startup checks, and this shortened Solis / Renon version follows that same pattern.

Inverter

Mount on a structural, fire-resistant surface.

Keep the unit vertical and maintain the Solis clearance diagram requirements.

Use only approved conduit entries and wiring paths for PV, battery, grid, backup, smart port, and communications.

Battery

Install on a suitable wall or floor-mount arrangement per Renon instructions.

Maintain service and ventilation space around the unit.

Follow the Renon mounting, grounding, and communications instructions exactly.

Step 1 — Mount the Solis Inverter

Install the factory mounting bracket on a structural wall.

Set the inverter plumb and secure it per the installation manual.

Verify working clearances before pulling conductors.

Step 2 — Install the Renon Battery

Mount the battery in the approved location and orientation.

Complete mechanical anchoring before landing conductors.

Connect PE / grounding, battery DC conductors, and communication cable per Renon’s wiring instructions.

Renon’s current user manual identifies the Xcellent Plus-US as an IP65 16 kWh, 51.2 V system with CAN / RS485 communications and gives the model specs used here.

Step 3 — Connect PV, Battery, Grid, Backup, and Communications

PV Wiring

Land PV strings on the inverter PV inputs.

Observe Solis polarity, string sizing, voltage, and current limits.

Use code-compliant disconnecting means and labeling.

Battery Wiring

Land the battery DC conductors on the inverter battery terminals.

Connect the Renon communication cable to the inverter battery communications port.

Confirm the battery model / protocol is supported by the current compatibility documentation before commissioning. Solis’s current US product materials also point installers to the battery matching / compatibility documentation for supported battery brands and models.

Grid / Backup / Smart Port

Land utility conductors at the grid port.

Land backed-up loads at the backup port.

Use the smart port for generator or controlled-load functions only when required by the project design.

Solis’s current local-settings and SolisCloud guidance explicitly includes storage mode settings, battery settings, smart port settings, and meter / CT settings as part of commissioning for this inverter family.

Step 4 — Verify Communications and Meter / CT Configuration

Confirm battery communications are healthy.

Confirm any required external meter / CT configuration is wired correctly and matches the commissioning settings.

Confirm no communication alarms are active before final startup.

Solis’s current Bluetooth / local-settings guides show battery selection, meter / CT configuration, grid code selection, storage mode settings, and battery settings as part of the required quick-setup flow.

Step 5 — Power-On Sequence

Before energizing the system confirm:

✔ Equipment securely mounted
✔ Conductors and communications connected
✔ Covers installed
✔ Unused ports sealed
✔ Battery ON and communication ready
✔ Meter / CT configuration verified if used

Startup Order

  1. Turn on the battery.
  2. Close the battery breaker / isolator if external.
  3. Energize inverter AC / grid supply.
  4. Turn on the inverter.
  5. Close PV isolator / DC input if present.
  6. Verify inverter boots normally and detects battery / grid / PV correctly.
  7. Complete commissioning immediately after startup.

Solis’s current installation and local-settings guides describe local Bluetooth connection, quick settings, battery setting, meter / CT setting, grid code setting, storage mode setting, and the ability to power the inverter on/off within the app settings flow.

Step 6 — Commissioning

Use the SolisCloud App.

Connect locally to the inverter via Bluetooth.

Set inverter time / date.

Select the correct battery model / battery settings.

Configure meter / CT settings as required.

Set the correct grid code.

Set storage / working mode.

Verify live values for PV, battery, load, and grid.

Confirm no battery communication alarms are present.

Solis’s current Bluetooth setup guide says first-time installer access is done in the SolisCloud app through More Tools → Local Operation → Connect with Bluetooth, then quick settings walk the installer through inverter time, battery model, meter placement, grid code, and storage mode. The same guide also describes battery settings, working modes, and information / alarm views.

Key Specifications

ParameterValue
Inverter familySolis S6-EH2P(9.6–16)K03-SV-YD-L-US
Inverter modelS6-EH2P16K03
Rated output16 kW
MPPT count3
Battery platform48 V low-voltage
Integrated pass-through / bypass200 A
Max battery-side currentUp to 290 A
Battery modelRenon Xcellent Plus-US
Battery chemistryLiFePO4
Battery nominal energy16 kWh
Battery nominal voltage51.2 V
Battery max charge / discharge current190 A
Battery communicationsCAN / RS485

These values come from Solis’s current US product page for the S6 hybrid family and Renon’s current Xcellent Plus-US product page / user manual.

Installer Tip

This guide is the shortened companion to the longer Solis / Renon field guide. It is intentionally condensed in the same way as the GoodWe example you shared, which also compresses system overview, mounting, wiring, startup, and commissioning into a short installer-facing reference.

Always verify system design, conductor sizing, OCP, battery compatibility, grid code, and commissioning settings against the latest manufacturer documentation before final startup. Solis’s currently published manuals and app guides are still actively updated, including a US inverter manual dated March 2026 and SolisCloud commissioning guidance updated in late 2025 / early 2026, so using the latest revision matters here.