Reviewing the Packing List and Confirming All Parts Were Received

Reviewing the Packing List and Confirming All Parts Were Received

Inventory your solar equipment promptly after delivery, even if installation is still weeks away. Finding a missing hardware bag or incorrect model early gives you time to resolve it before work begins.

The packing list identifies what a shipment is recorded as containing. Your physical inventory confirms what actually arrived. Neither replaces the approved plan set or the complete project purchasing list.

Reconcile your purchase documents, packing lists, and latest approved plans—and keep locally purchased materials separate from supplied kit contents.

Understand what each document tells you

DocumentWhat it establishes
Order confirmation and approved order changes          Equipment and quantities included in your purchase
Shipment notice and tracking information           Which deliveries to expect and any identified separate shipments
Packing list          Items recorded as packed in that particular shipment
Physical inventory         Actual items, quantities, identifiers, and condition received
Approved plan set and equipment schedule         Equipment and installation requirements for the project
Full project purchasing list         Supplied, locally purchased, and contractor-supplied materials needed to complete the installation

Use the latest revisions. If the order, packing list, and plans disagree, flag the difference for review rather than choosing one document and ignoring the others.

Start with delivery inspection

Before unpacking, document the shipment's condition and any visible damage or shortages. Keep the delivery receipt, shipping labels, and photographs together with your order records.

Inventory and damage inspection are related but separate checks. A product can be present and still be damaged or incorrect. Record both quantity and condition; do not count a damaged item as ready for installation.

Retain packaging for any missing-part or damage investigation. Do not install or energize equipment suspected of shipping damage.

Inventory one shipment and package at a time

Set up a clean, dry area with room to sort small parts without mixing packages. Assign each box or pallet an identifier if it does not already have one, and record where its contents will be stored.

Open packages methodically, preserve labels, and check each item against the relevant packing-list line. Photograph labeled contents before redistributing them into storage bins. Keep small hardware in its original labeled bags whenever practical.

Do not assume the first delivery completes the order. Modules, racking, electrical equipment, and accessories may arrive separately. Track each shipment individually, then reconcile the combined totals against the order. A separate shipment is confirmed by shipping information or our support team—not simply by an item being absent.

Inventory in four layers

1. Major equipment

Count the modules, inverters or microinverters, batteries, combiners, controllers, gateways, and racking rails specified in your order.

Record manufacturer, complete model or part number, quantity, and serial numbers for serialized equipment. For rails and similar materials, also verify the specified length or size. Compare carton labels with accessible product labels when practical, without unsafe handling or opening sealed equipment housings.

Similar names, appearance, or wattage do not establish that the correct product arrived. Include model suffixes and other identifiers shown on the label.

2. Mounting hardware

Work through the racking bill of materials for your particular mounting system. Items may include roof attachments, flashings, L-feet, clamps, splices, end caps, stopper sleeves, grounding lugs, bonding hardware, and fasteners.

Not every mounting system uses every item on that list. Check the specified assembly rather than assuming a familiar part must be present.

Pay attention to quantity units. A packing-list quantity of “2” might mean two individual parts, two bags, or two complete kits. Record the number of packages and the stated contents per package, then confirm the actual count as appropriate. If a sealed package's contents cannot be verified without disrupting protective packaging, mark it “contents not yet verified” and request guidance if needed.

For bundled assemblies, check the kit contents list before treating a component as missing or counting it again as a separate item. Do not infer fastener quantities from bag weight or assume extra-looking hardware is surplus.

3. Electrical accessories

Check the cable and accessories included in your order. Depending on the system, these may include PV cable, Enphase IQ/Q cable, branch terminators, watertight caps, cable glands, current transformers (CTs), communications accessories, and labels.

Verify cable lengths, connector types, and quantities against the order descriptions. Check whether an accessory is factory installed, packaged with a larger product, or shipped separately. A gateway function or other feature may be integrated into supplied equipment rather than provided as a standalone device.

Keep these kit boundaries in mind:

  • PV string systems: Applicable kits include PV wire with MC4 connectors to reach the array junction box.

  • Enphase systems: The specified IQ/Q cable, branch terminators, project-specific watertight caps or extra cable drops, and array junction-box cable glands are included.

  • Disconnects: IMO rotary DC disconnects are supplied when specified on the plans. Required AC disconnects, fused or non-fused, are purchased separately.

  • Local electrical materials: The array junction box, home-run wiring, conduit, fittings, straps, and breakers are purchased separately.

  • Ground mounts: The specified IronRidge components are supplied; support pipe and concrete are purchased locally.

  • Labels: A standard solar NEC PV labels kit is included. Custom site placards and required supplemental labels are purchased separately.

Do not report a locally sourced item as a kit shortage. If the responsibility for a tool, control, or accessory is unclear, mark it for confirmation rather than assuming it is included.

4. Documentation and commissioning information

Confirm that you have access to the current plan set, equipment instructions, warranty information, and any required commissioning information. Manuals may be supplied electronically or through a manufacturer link or QR code; absence of a printed booklet does not necessarily indicate a shortage.

Preserve serial-number and commissioning labels. Store account setup information or credentials securely, and keep product identification labels attached to the equipment.

Keep planned local purchases in a separate section or clearly mark their purchasing responsibility. Avoid counting the same accessory once inside an equipment package and again as a separate packing-list line.

Resolve model differences before installation

If a delivered model differs from your order or approved plans, do not assume it is a newer equivalent. A substitution may affect dimensions, mounting, electrical ratings, rapid shutdown, structural loading, equipment compatibility, or permit approval.

Photograph the delivered product label and identify the model expected by the order and plans. Request confirmation from us and the system designer before installing the affected equipment. Update the order records and obtain a plan or permit revision when required.

Keep written approval with the project records. Availability, similar wattage, or a verbal description of “equivalent” is not enough to resolve a documented mismatch.

Report missing or incorrect parts promptly

If your count does not match the expected contents:

  1. Record the discrepancy. Note the expected quantity, received quantity, part number, package identifier, and whether the issue is a shortage or an incorrect item.

  2. Check the packaging and shipment records. Look in labeled small-parts boxes and accessible accessory compartments identified by the unpacking instructions. Check for separate-shipment or backorder information. Do not open sealed electrical housings to search for parts.

  3. Photograph what arrived. Include the contents, package labels, packing-list reference, and relevant product labels.

  4. Contact us promptly. Provide your order number, item description, part number, quantities, shipment reference, and photos. Report what you know without waiting until every unrelated package has been inventoried.

  5. Track the resolution. Record any confirmed additional shipment, replacement, corrected part identification, or approved change. Recheck the worksheet when the item arrives.

Do not wait until installation day to report a discrepancy, and do not purchase an assumed replacement before confirming the correct part and next steps with us. Keep unresolved items visible on the worksheet until the physical inventory and project records agree.

Packing-list checklist

  • Each delivery is matched to its packing list and shipment information.
  • Major equipment quantities and complete model numbers are verified.
  • Mounting hardware is checked against the correct racking bill of materials.
  • Package quantities and individual-part quantities are distinguished.
  • Electrical accessories are checked, including bundled or factory-installed items.
  • Serial numbers are recorded for serialized equipment.
  • Required instructions and commissioning information are accessible.
  • Separate shipments and backorders are confirmed and tracked.
  • Model differences are resolved with written approval and plan updates where required.
  • Missing, incorrect, and damaged items are reported promptly.
  • Locally purchased and contractor-supplied materials are tracked separately.
  • Verified parts are labeled and stored so they can be found on installation day.

A complete inventory confirms more than the number of boxes: it establishes that the correct parts, quantities, and documentation are available for the approved installation.