Plan, Permit & Procure: Everything You Need Before You Break Ground

Plan, Permit & Procure: Everything You Need Before You Break Ground

Click Here for a video walk through


Plan, Permit & Procure: Everything You Need Before You Break Ground
​
A successful DIY solar project is usually won or lost before installation day. Phase 1 is about making sure the property is suitable, the system design matches actual site conditions, required approvals are underway or complete, and the equipment, materials, labor, and safety needs are organized before work begins.

The three tracks

1. Plan

Confirm your goals, energy use, roof or ground-mount location, electrical service, equipment placement, and installation approach.

Complete the site survey and make sure the final design reflects actual field conditions, including roof dimensions, structural considerations, electrical-panel details, and equipment locations.

2. Permit

Submit the plan set and required forms to the authority having jurisdiction (AHJ).

Respond to any plan-check comments or required corrections and obtain the permit before beginning work that requires approval.

Your utility interconnection application and any HOA or architectural approval are separate processes. They may be completed in parallel with permitting when their rules allow.

3. Procure

Coordinate equipment delivery with your project schedule. When practical, avoid committing to nonreturnable equipment or final purchases until the design and permit requirements are confirmed.

When equipment arrives, inspect it for damage and compare all items with the packing list and approved design.

Use the approved plans to purchase the remaining balance-of-system (BOS) materials, such as wire, conduit, fittings, breakers, disconnects, junction boxes, concrete, pipe, and specialty roof hardware.

Any equipment substitutions should remain code-compliant and be approved by the designer, AHJ, or utility when required.

  1. Confirm that the roof has adequate remaining service life and that the roof or ground-mount location is structurally suitable for the proposed system. Obtain a professional evaluation when required.
  2. Complete the site survey. Provide clear photos, measurements, roof information, equipment locations, and electrical-panel details.
  3. Review the preliminary design and confirm that it matches actual site conditions before the plans are finalized.
  4. Submit the permit package and respond to any plan-check comments or corrections.
  5. Do not begin installation from an unapproved draft when a permit is required.
  6. Coordinate equipment delivery and inspect all equipment when it arrives.
  7. Build a local purchasing list from the approved single-line diagram (SLD), conduit schedule, equipment schedule, and mounting details.
  8. Purchase the required local BOS materials.
  9. Schedule helpers, lifting assistance, fall-protection equipment, and any work that must be performed by a licensed electrician or other qualified trade under local requirements.
  10. Start installation only after required approvals, materials, tools, labor, and safety controls are ready.

Phase 1 exit checklist

☐ Site survey is complete and accurate.

☐ Roof, structure, and electrical service are suitable, or required upgrades have been identified.

☐ Final plan set matches the property and selected equipment.

☐ Required permit has been issued.

☐ HOA or architectural approval is complete when applicable.

☐ Utility interconnection application has been submitted when required.

☐ Major equipment has been inspected and inventoried.

☐ Required local BOS materials have been purchased from the approved plans.

☐ Any equipment substitutions have been approved when required.

☐ Tools, safety equipment, helpers, and required licensed trades are scheduled.

☐ The project is ready to begin installation safely and in accordance with the approved design.

Important: The approved plan set, manufacturer instructions, permit conditions, and the requirements of your AHJ and utility take precedence over general guidance in this knowledge base.