Enphase IQ Meter Collar: Meter Socket and Installation Requirements

Enphase IQ Meter Collar: Meter Socket and Installation Requirements

Overview-

The Enphase IQ Meter Collar is designed for use with a standard ANSI C12 Form 2S meter socket rated for 200 A continuous service.

The collar may be installed in either of the following locations:

• Behind the utility meter
• In a separate load-side meter socket dedicated to the collar

Both ring-type and ringless meter bases may be used, depending on the socket configuration and local utility requirements.


Enphase Meter Socket Option-

For installations using a separate meter socket, Enphase offers the following:

• Model/SKU: MP-MC-200
• Type: 200 A ringless meter socket

Published enclosure dimensions:

• 15.2 inches deep
• 11.3 inches wide
• 4.5 inches high
• 200 A continuous rating


Knockout Location Information-

Enphase does not publish the bottom knockout centerline locations for the MP-MC-200 meter socket.

These dimensions are typically provided by the meter socket manufacturer in the enclosure drawing or product submittal, not in the IQ Meter Collar documentation.


Feeder Rearrangement Planning-

Before planning conduit or feeder routing:

• Select the exact meter socket model.
• Obtain the manufacturer's dimensional drawing or product submittal.
• Verify:
• Knockout sizes
• Knockout centerline locations
• Distance from the rear mounting surface
• Distance from enclosure edges

These dimensions are necessary for accurate conduit and conductor layout.


Control Wiring-

The IQ Meter Collar installation guide includes provisions for a 1/2-inch liquid-tight conduit connection for control wiring.

This conduit connection is separate from the service-conductor knockouts in the meter socket.


Utility Coordination-

Before installing the IQ Meter Collar behind the utility meter, confirm that the serving utility approves its use.

A separate load-side meter socket may eliminate the need to mount the collar on utility-owned equipment. However, utility coordination is still typically required to disconnect and restore service during installation.

    • Related Articles

    • Enphase IQ8 Series Installation and Operations Manual

      The Enphase IQ8 Series Installation and Operations manual is attached to this post. This manual serves as a comprehensive guide for the installation and operation of Enphase IQ8 Series products. It provides detailed instructions, guidelines, and ...
    • Enphase IQ Battery 10C Training (4th Gen)

      This Article is to help guide you through the Enphase online training, which is necessary to complete the installation of your solar system with Enphase IQ batteries. To complete the Enphase Encharge certification process, you will need to go through ...
    • Enphase IQ Battery 5P Training (3rd Gen)

      This Article is to help guide you through the Enphase online training which is necessary to complete the installation of your solar system with Enphase IQ batteries. In order to complete the Enphase Encharge certification process, you will need to go ...
    • How-to commission a Enphase IQ Battery Storage system using the Enphase Installer App

      Step by step full comissioning video for Enphase IQ Battery Systems Watch the video below for a full commissioning sequence for the installation and commissioning of a Enphase Battery Storage system with System Controller 2 via the Enphase Installer ...
    • IronRidge Rooftop Installation Video

      How to Install the IronRidge Racking System Check out the short video below to learn how to install the IronRidge Racking System on a rooftop. This video will go over the basics of the IronRidge Racking System. For more detailed instructions download ...