Conducting a Complete Solar Site Survey

Conducting a Complete Solar Site Survey

A site survey turns a preliminary or remote solar design into a project that can be permitted and built. Incomplete measurements, missing equipment information, or unclear photographs can lead to permit corrections, design revisions, equipment changes, inaccurate material estimates, and installation delays.

Companion Resource

Before completing the survey, review the GoGreenSolar DIY Solar Installation Guide for an overview of the planning, permitting, installation, inspection, and interconnection process.

This resource supplements—not replaces—the project-specific survey form, approved plans, manufacturer instructions, and local requirements.

Information to Capture

Property and Roof

  • Installation address and applicable authority having jurisdiction (AHJ)
  • Roof-covering type, approximate age, slope, number of stories, and visible condition
  • Dimensions and orientation of each proposed roof plane
  • Shading and obstructions, including ridges, hips, valleys, skylights, vents, chimneys, and other rooftop equipment
  • Distances to roof edges, ridges, valleys, and obstructions needed to evaluate applicable setbacks and access pathways
  • Attic access and visible framing information, including framing type, member size, spacing, span or support locations, direction, and apparent condition
  • Available structural or construction documents, when applicable
  • Any visible signs of leakage, sagging, deterioration, fire damage, or previous structural alterations

Electrical System

  • Utility provider, meter number, and other account information required for interconnection
  • Utility meter location and service configuration
  • Main service equipment manufacturer, model, listed rating, main-breaker rating, bus rating, and available breaker spaces
  • Clear photographs of equipment labels, the meter, service equipment, and panel directory
  • Subpanels, generators, transfer switches, existing solar or storage equipment, and other interconnected power sources
  • Proposed point of interconnection and any known utility-specific requirements

Keep electrical equipment covers closed unless an interior inspection is necessary and is performed by a qualified person using appropriate electrical-safety procedures. Unqualified persons should not remove covers or approach exposed energized components.

Equipment Locations and Routing

  • Proposed locations for inverters, batteries, combiners, disconnects, gateways, and other balance-of-system equipment
  • Required equipment access and working clearances
  • Wall construction, mounting surface, and surrounding environmental conditions
  • Approximate conduit and conductor routes, including estimated lengths
  • Attic, crawlspace, exterior-wall, trench, and roof-transition locations
  • Potential routing conflicts or concealed areas that could not be inspected
  • Internet, Wi-Fi, Ethernet, or cellular availability when required for commissioning or monitoring

Confirm that each proposed equipment location complies with the manufacturer’s installation instructions, the approved design, and applicable local requirements.

Photo Standards

Take photographs at three levels:

  • Wide views showing the building, roof planes, and overall equipment locations
  • Medium-distance views showing relationships between equipment, obstructions, and proposed routes
  • Close-ups showing labels, dimensions, construction details, and visible conditions

Keep photographs upright, well lit, in focus, and clearly labeled. Include a tape measure or other reliable scale where dimensions are important. Do not rely on photographs alone when a recorded measurement is required.

Example Completed Survey

  • Project: Sample Residence, 123 Example Lane
  • Roof: Composition shingles, approximately eight years old; 5:12 slope; two stories; no visible signs of active leakage at the time of the survey
  • Framing: Nominal 2 × 6 rafters spaced 24 inches on center and running from ridge to eave; visible condition documented
  • Main service equipment: Outdoor meter-main; 200-ampere bus rating; 200-ampere main breaker; two unused breaker spaces; manufacturer and model documented
  • Proposed array: South- and west-facing roof planes; one plumbing vent and one skylight measured and photographed
  • Proposed equipment location: North garage wall; mounting surface and required working clearances documented
  • Proposed conduit route: Roof junction box through the attic, then down the garage wall to the equipment; estimated route length of 55 feet
  • Special conditions: HOA review may be required; no existing generator observed; weak Wi-Fi signal at the proposed equipment location

Submission Checklist

  • Every required field is complete or marked “not applicable.”
  • Measurements use consistent units and identify how they were obtained.
  • Roof planes, obstructions, setbacks, and proposed array areas are documented.
  • Framing observations and available structural information are recorded.
  • Electrical-equipment ratings and labels are readable.
  • Photographs are upright, focused, labeled, and sufficient to establish context.
  • Proposed equipment locations and routing are clearly marked.
  • Existing solar, storage, generators, and transfer equipment are documented.
  • Safety hazards and inaccessible areas are identified.
  • Conflicts, discrepancies, and uncertainties are clearly noted rather than estimated or omitted.

A site survey records observed conditions; it does not replace structural analysis, electrical design, or field verification during installation. If actual conditions differ from the approved plans, obtain clarification or a design revision before proceeding.